February 2003 photos of the Main Library Project
click on photos for larger images

Painting and the installation of the ceiling grid has started on the first and second floors.
2/13/03
Face brick work continues on the Lake Street (south) side of the building.
2/13/03

Exterior stone work continues on the north east corner.
2/13/03
Stud framing is complete at the curtain wall on the east side.
2/13/03

View of the first floor lobby looking towards the future Circulation Desk area.
2/20/03
Ceiling grid is being installed in the first floor children's area.  The circular wall opening is intended for an aquarium.
2/21/03
Glass has been installed on the first floor east side of the building.
2/21/03
Exterior stone work continues on the south side, along Lake Street, under temporary plastic plastic winter protection.
2/21/03

Insulation being installed in the walls of the second floor art gallery.
2/20/03
View of the copper roof and the cement area to be filled with dirt for the green roof.
2/21/03
Insulation is being installed on the exterior walls of the east side of the building.
2/21/03

Stone work is complete on portions of the north east corner.
2/28/03
Window frame installation has begun on the second floor east side.
2/28/03

Window frames on the first floor south side have been installed under the temporary plastic winter protection.
2/28/03

January 2003 photosarrow

arrowMarch 2003 photos