November 2002 events in
the Main Library Project
East Side of Third Floor
Roof Takes Shape
The
Meyne Company began to cover openings with temporary plastic to protect
the interior of the building from the weather. Vertical steel tube columns
to support the third floor roof were installed on the east side. The Meyne
Company completed installation of half the glulam beams, wrapped in green
protective plastic, which will form the interior roof beams. Installation
of glulam decking, the interior third floor roof, is scheduled to begin
the first week of December. In November the Meyne Company also started
cast stone base and face brick work on the north side. Inside, workers
began to work with metal studs and interior block on the first floor and
ductwork and piping continued on all floors.