Oak Park Public Library

Home > Main Library > Construction > Timeline > July 2002


Timeline

1999
October
December

2000
January
March
July
August
September
October
December
2001
January
February
March
May
August
October
November
December

2002
January
February
March
April
May
June
July
September
October
November
December

2003
January
February
March
April
May
June
July
September
October

July 2002 events in the Main Library Project

Building On Schedule, Permit Process Continues
The formwork for the concrete walls is prepared.  (Click for larger image.)The Meyne Company is making steady progress and the building is on schedule. Installation of sixty caissons, 45-foot deep concrete tubes on which the foundation of the new building will be set, was completed. Only three or four of the caissons encountered obstacles (i.e. rocks). The Meyne Company erected concrete forms and the majority of the basement walls and columns were poured. A “full” building permit is still in the process of being obtained. To obtain this permit plans must pass review in several areas including building, mechanical, electrical, plumbing, and fire safety.

More Construction Photos:
Site Work - May June July
Concrete Work - July Aug Sept Oct
The north wall and part of the east wall have been poured for the basement level.