January 2003 events in the
Main Library Project
Exterior Shapes Up
Window
glass was installed on the north side and was started on the west side
of the building. Face brick work was completed on the penthouse level
and is nearing completion on the west side. Exterior stone work was started
on the north east corner. The Meyne Company began construction of the
first floor exterior wall on the east side. Inside, workers continued
drywalling on the first, second, and third floors and began installation
of the custom staircase.