Oak Park Public Library

Home > Main Library > Construction > Timeline > December 2002


Timeline

1999
October
December

2000
January
March
July
August
September
October
December
2001
January
February
March
May
August
October
November
December

2002
January
February
March
April
May
June
July
September
October
November
December

2003
January
February
March
April
May
June
July
September
October

December 2002 events in the Main Library Project

Topping Out Ceremony
Sun setting on Scoville Park viewed from the third floor of the new main library building.  (Click for larger image.)On Monday, December 9, 2002 at 3:00 p.m. the Library Board of Trustees was joined by village representatives for a brief topping out ceremony at the site of the new main library building. The final glulam decking is expected to be installed on the the third floor roof later in the week to complete the roof top of the building. Since stairways and elevators are still in construction those that attended the ceremony were transported to the third floor via lift. Library Board President, John Hayes, remarked that the building project is continuing according to the projected timeline and that feat is a result of the commendable cooperation of the many parties involved. He also is looking forward to sitting in the completed building and looking at the beautiful view of Scoville Park. Ed Byers, Executive Director of the Library, thanked those involved for making it such a successful process. To mark the occasion those in attendance signed their names to a third floor concrete column that will be covered in the finished building.

Ed Byers thanks those involved in the construction project. John Hayes addresses those gathered under a portion of the glulam decking.
Township Supervisor David Boulanger signs his name to mark the historic occasion. The participants pose against the backdrop of Scoville Park.

Work Progresses on All Sides
Working under winter protection the Meyne Company completed the face brick on the north side of the building. Brick work was started on the west side and the penthouse level. The Meyne Company also started window frame installation on the north side and installation of metal studs at the first floor feature wall.

The most visible work of the month was the the installation of the glulam beams and decking to complete the roof on the east side of the building. Work behind the scenes included the pouring of the concrete slab on the basement parking garage level, installation of the book return conveyor, and setting of the air handler and chillers.

More Construction Photos:
Exterior Masonry - Nov Dec Jan
Roofing - Nov Dec
Feb
Workers on lifts work with the glulam decking and glulam beams (here, still wrapped in green plastic).